Sunday 23 September 2012

Week 11










Another busy week on site, the painting is now finished, the work surfaces are in, the laundry cupboard and sink are in, the kitchen sink is in, window sills are finished, downpipes are  fitted, and the tiling was set to be finished by the end of the weekend!

I had an email letting me know that they anticipate having the 'fit offs' complete within 2-3 weeks (mainly electrical and plumbing), then its just the carpet and timber flooring (and a few smaller tasks). We are loving seeing all the progress being made every week now. Fingers crossed it wont be too long now, until we can move our little family in.